By considering following activities of a project, the project duration will be: \[Table: A(4), B(5), C(3), D(7), E(5) days, predecessors: A:-, B:-, C:-, D:C, E:A,B,D] <figure><img src="https://1335304073-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2F6BUDIDLBlnJ37FLFExZ6%2Fuploads%2FVgNdNIoj6Sy8GVjkOPj4%2Fimage.png?alt=media&token=766f5ee6-147d-4cf0-b5ed-33b08a0487f3" alt=""><figcaption></figcaption></figure>