By considering following activities of a project, the project duration will be: \[Table: A(4), B(5), C(3), D(7), E(5) days, predecessors: A:-, B:-, C:-, D:C, E:A,B,D] <figure><img src="https://2192968881-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FA9j5jkcDSyh4kRyuGhhN%2Fuploads%2F49xgtwEqwM1yOnScjV47%2Fimage.png?alt=media&token=c6ff767d-2fd2-48d5-bd48-cf2b9dc78e2d" alt=""><figcaption></figcaption></figure>