NEC licence exam preparation, made clearer.Practice questions, syllabus guides, and timed mocks for Nepal engineers.New study resources are added regularly.NEC licence exam preparation, made clearer.Practice questions, syllabus guides, and timed mocks for Nepal engineers.New study resources are added regularly.
Project planning and scheduling Past-paper practice · set-8-poush-2081
1 questions
Question 1
A PERT network has nine activities on its critical path. The standard deviation of each activity on the critical path is 3. The standard deviation of the critical path is: