Hydropower project planning Set 6 ashoj 2081 | NEC Civil
Latest notices:
NEC licence exam preparation, made clearer.Practice questions, syllabus guides, and timed mocks for Nepal engineers.New study resources are added regularly.NEC licence exam preparation, made clearer.Practice questions, syllabus guides, and timed mocks for Nepal engineers.New study resources are added regularly.
Two turbo-generators, each of capacity 25,000 kW, have been installed at a hydel power station. The load on the hydel plant varies from 15,000 kW to 40,000 kW. The total installed plant capacity and the load factor are nearly: