Home›Question bank›Project PlanningNEC Common | 2083 | Question 4The critical path represents:Engineering Professional Practice / Project Planning and SchedulingAThe maximum duration in which the project can be completedBThe minimum duration in which the project can be completedCDoes not signify project completionDThe mean time in which the project can be completedChecking answer access…Report a question issueTell us what needs checking.Issue typeIncorrect answerMissing or unclear diagramFormatting problemQuestion or explanation unclearOtherDetails (optional)Review and send the email draft in Gmail. Nothing is sent automatically.Open Gmail draft Copy report detailsReports go to hello@licensepreparationnepal.com.