NEC Common | 2083 | Question 15

A schedule performance index (SPI) of 0.76 means:

Engineering Professional Practice / Project Planning and Scheduling

AYou are over budget
BYou are ahead of schedule
CYou are only progressing at 76 percent of the rate originally planned
DYou are only progressing at 24 percent of the rate originally planned