Home›Question bank›Project PlanningNEC Common | 2083 | Question 15A schedule performance index (SPI) of 0.76 means:Engineering Professional Practice / Project Planning and SchedulingAYou are over budgetBYou are ahead of scheduleCYou are only progressing at 76 percent of the rate originally plannedDYou are only progressing at 24 percent of the rate originally plannedChecking answer access…Report a question issueTell us what needs checking.Issue typeIncorrect answerMissing or unclear diagramFormatting problemQuestion or explanation unclearOtherDetails (optional)Review and send the email draft in Gmail. Nothing is sent automatically.Open Gmail draft Copy report detailsReports go to hello@licensepreparationnepal.com.