Home›Question bank›Project PlanningNEC Common | 2083 | Question 12The company or project initiated through two or more parties is called:Engineering Professional Practice / Project Planning and SchedulingABilateral ProjectBMultilateral projectCJoint Venture projectDPPPChecking answer access…Report a question issueTell us what needs checking.Issue typeIncorrect answerMissing or unclear diagramFormatting problemQuestion or explanation unclearOtherDetails (optional)Review and send the email draft in Gmail. Nothing is sent automatically.Open Gmail draft Copy report detailsReports go to hello@licensepreparationnepal.com.