NEC Common | 2083 | Question 11

The optimistic, most likely and pessimistic activity estimates are 5, 10 and 21 days. What are the expected time and standard deviation?

Engineering Professional Practice / Project Planning and Scheduling

A12, 3
B11, 4
C11, 2.67
D10, 16