NEC Civil · 2081 · Question 78

For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is

GitBook practice — Set 8 (Poush, 2081)

A8 days
B9 days
C10 days
D15 days