NEC Civil · 2081 · Question 53

A PERT network has nine activities on its critical path. The standard deviation of each activity on the critical path is 3. The standard deviation of the critical path is:

GitBook practice — Set 8 (Poush, 2081)

A3
B81
C27
D9