Pick up the incorrect statement from the following:

GitBook practice — Set 4 (Ashadh, 2081)

AThe difference between the earliest start time and latest finish time of any activity, is the maximum time available for the activity
BThe difference between the maximum time available for the job and actual time it consumes, is called total float
CThe difference between the earliest finish time of an activity and the earliest start time of its successor activity, is called free float of the activity
Dnone of these