Question 1Average usage is 20 units per day, lead time is 5 days and safety stock is 30 units. What is the reorder point?Report a question issueTell us what needs checking.Issue typeIncorrect answerMissing or unclear diagramFormatting problemQuestion or explanation unclearOtherDetails (optional)Review and send the email draft in Gmail. Nothing is sent automatically.Open Gmail draft Copy report detailsReports go to hello@licensepreparationnepal.com.A.100 unitsB.130 unitsC.150 unitsD.50 units
Question 2Which costs are balanced in the basic EOQ model?Report a question issueTell us what needs checking.Issue typeIncorrect answerMissing or unclear diagramFormatting problemQuestion or explanation unclearOtherDetails (optional)Review and send the email draft in Gmail. Nothing is sent automatically.Open Gmail draft Copy report detailsReports go to hello@licensepreparationnepal.com.A.Marketing and warrantyB.Tax and insurance onlyC.Depreciation and labor onlyD.Ordering and holding
Question 3For D = 1000/year, order cost 20, and holding cost 4/unit/year, what is EOQ?Report a question issueTell us what needs checking.Issue typeIncorrect answerMissing or unclear diagramFormatting problemQuestion or explanation unclearOtherDetails (optional)Review and send the email draft in Gmail. Nothing is sent automatically.Open Gmail draft Copy report detailsReports go to hello@licensepreparationnepal.com.A.50 unitsB.200 unitsC.100 unitsD.500 units
Question 4Demand averages 20 units/day and lead time is four days. With no buffer, what is the reorder point?Report a question issueTell us what needs checking.Issue typeIncorrect answerMissing or unclear diagramFormatting problemQuestion or explanation unclearOtherDetails (optional)Review and send the email draft in Gmail. Nothing is sent automatically.Open Gmail draft Copy report detailsReports go to hello@licensepreparationnepal.com.A.80 unitsB.5 unitsC.20 unitsD.100 units
Question 5A reorder point is 120 units and mean lead-time demand is 95. What safety stock is planned?Report a question issueTell us what needs checking.Issue typeIncorrect answerMissing or unclear diagramFormatting problemQuestion or explanation unclearOtherDetails (optional)Review and send the email draft in Gmail. Nothing is sent automatically.Open Gmail draft Copy report detailsReports go to hello@licensepreparationnepal.com.A.215 unitsB.120 unitsC.95 unitsD.25 units
Question 6What is procurement lead time?Report a question issueTell us what needs checking.Issue typeIncorrect answerMissing or unclear diagramFormatting problemQuestion or explanation unclearOtherDetails (optional)Review and send the email draft in Gmail. Nothing is sent automatically.Open Gmail draft Copy report detailsReports go to hello@licensepreparationnepal.com.A.Time between two forecasts onlyB.Time stock stays unsoldC.Time from order placement to availabilityD.Time needed to calculate EOQ
Question 7What normally puts an item into class A under ABC inventory analysis?Report a question issueTell us what needs checking.Issue typeIncorrect answerMissing or unclear diagramFormatting problemQuestion or explanation unclearOtherDetails (optional)Review and send the email draft in Gmail. Nothing is sent automatically.Open Gmail draft Copy report detailsReports go to hello@licensepreparationnepal.com.A.Longest product nameB.High annual consumption valueC.Largest package volumeD.Most common shelf color
Question 8What is the three-period moving average of 90, 120 and 150?Report a question issueTell us what needs checking.Issue typeIncorrect answerMissing or unclear diagramFormatting problemQuestion or explanation unclearOtherDetails (optional)Review and send the email draft in Gmail. Nothing is sent automatically.Open Gmail draft Copy report detailsReports go to hello@licensepreparationnepal.com.A.110B.90C.150D.120
Question 9In simple exponential smoothing, what does a higher α do?Report a question issueTell us what needs checking.Issue typeIncorrect answerMissing or unclear diagramFormatting problemQuestion or explanation unclearOtherDetails (optional)Review and send the email draft in Gmail. Nothing is sent automatically.Open Gmail draft Copy report detailsReports go to hello@licensepreparationnepal.com.A.Respond more strongly to recent demandB.Force the forecast to be constantC.Give all past periods equal weightsD.Ignore the most recent demand
Question 10What is the difference between reorder point and order quantity?Report a question issueTell us what needs checking.Issue typeIncorrect answerMissing or unclear diagramFormatting problemQuestion or explanation unclearOtherDetails (optional)Review and send the email draft in Gmail. Nothing is sent automatically.Open Gmail draft Copy report detailsReports go to hello@licensepreparationnepal.com.A.Both always represent lead time in daysB.One measures unit cost and the other sales taxC.One triggers an order and the other sets its sizeD.They must be equal in every system